| Who Needs This Permit? |
| |
Anyone who has applied to build a new building, or an addition to an
existing building, receives this Permit as part of the Building
Permit approval process.
|
| Issuing Municipality: |
| |
Town of
Oxford
|
| Where can you get this
Permit and / or further information?: |
| | Contact: |
Building Inspector
Town of Oxford |
| |
Phone: |
(902) 447-2170 |
| |
Visit: |
Town Office
5201 Main St.
Oxford, NS |
| |
E-mail: |
townhall@town.oxford.ns.ca
|
| |
Write: |
PO Box 338
Oxford, NS
B0M 1P0 |
| |
Fax: |
(902) 447-2485
|
| Application Forms
& Process: |
| |
You do not have to make any separate application for this Permit; it
is a part of the Building Permit approval process.
You have to provide a Location Certificate when the footing(s) are complete.
|
| Waiting Period: |
| |
Once the Location Certificate has been received, and inspection is carried
out for compliance and the work approved, the final Building Permit will
be issued with 3-5 days.
|
| Price: |
| |
Free (It is included in the fee for the Building Permit.)
|
| Expiry & Renewal: |
| |
The Permit is valid for one year from the date it is issued. It can be
renewed. It is the responsibility of the Permit holder to contact the
Municipality before it expires; NO NOTICE of renewal will be sent out
by the Municipality.
|
| Related Requirements: |
| |
The issuance of this permit is part of the Building
Permit approval process.
|
| Additional Information: |
| |
None
|
| Legislative Authority: |
| |
Building Code Act, Chapter 46, of the Revised Statutes of Nova Scotia, 1989.
|